The third semester of the project saw the enlargement of the Consortium by two new partners University of Zürich and Be Informed. While the original planned start of the MOLTO-EEU project enlargement was scheduled for September 2011, and accounted for synchronicity of the deliverables with ongoing workpackages, the actual kickoff only happened in January 2012. Consequently, the end date of the project is now shifted to 31 May 2013 and the main deliverable of Workpackage 2 has been shifted 3 months to take into account the feedback from the new use cases added by the enlargement.
The following inconsistencies have been noticed in the revised Annex:
However, due to the delay in start, both WP11 and WP12 will now be ongoing in the period M22-M37, as in the chart below. Notice also the changes affecting WP2 and WP8.