WP12 Interactive knowledge-based systems - M3
Summary of progress
The first 2 months we started with the Adoption phase as described in the DoW for WP12. We've focused our efforts on the requirements for the verbalization component(D12.1). We distinguish 4 categories of relevant requirements.
- Ontology verbalization
- Sentence Variants generation
- Adopt of GF in Be Informed modelling process
- Adopt GF in interactive applications for integration generated text
We presented a requirements draft to our partners in March 2012.
At the kickoff hosted by UGOT we did a first round with the UGOT people to draw up the specification to migrate Be Informed current explanation prototype to GF.
Next Steps
- Finalize requirements for D12.1
- Migrate current explanation engine to GF
- Train Be Informed co workers in GF
- Start development of business domain related abstract grammars.
Highlights
- Kickoff MOLTO-EEU
- Started requirements for verbalization component. Draft Outline shared with Partners M3.
- Started a joint paper with Monnet and MOLTO partners. The article focuses on the GF (MOLTO) and lemon(MonnetO integration in ontology lexicalization and verbalization.
Use of resources
Node | Professor/Manager | PostDoc | PhD Student | Research Engineer/Intern |
---|---|---|---|---|
UGOT | 0 | 0 | 0 | 0 |
BI | 0,25 (J. van Grondelle, J. van Aart ) | 0 | 0 | 0,25 (H. ter Horst) |
Deviations from Annex I
WP12 runs longer than is indicated in the Gantt chart appearing in the Annex, however duration is correctly listed under 3.3.3. We planned for a duration of 15 months, D12.2 for instance is projected for March 2013.